Global Energy Group were awarded the contract for the installation of a pennant line that was to be deployed from the vessel side down into the water where a diver connected the pennant line to a dedicated padeye on the underside of the FSU turret.

On arrival at the site, the client carried out the various inductions for the team.  Personnel arrived at NEP at the start of the shift and transited to site on the MV Equinox. The Diving vessel moored up adjacent to the Mariner FSU to allow operations to be carried out safely. The pennant line was installed using a 12Te WLL shackle followed by a Diver video survey of the FSU thrusters.  All operations were carried out in a safe and timely manner with no incidents or accidents recorded. Operations were carried out in a safe and efficient manner, with zero incidents or accidents recorded.

Project Mariner FSU – Pennant Line Installation
Customer Statoil
Location Nigg Energy Park
Asset MV Equinox
Depth <10m